SITE SETOUT

Function

Potential problems

1) Cases have happened especially on greenfield sites where a building is positioned outside plot boundaries. Or the building placed too close to fences, boundary walls or above sewers.
Also, cases have been witnessed where the actual dimensions of the building are wrong resulting in a bigger or smaller building in comparison to the one planned

Materials, Plant labour requirements

Dumpy levels, timber boards, lines, water lines, tape measures
Skilled surveyor is required to transfer the building from the drawing/floorplan to the ground.

2.4 Procedure for site setting out

  • Study and internalize the drawings;
  • Physically measure out the plot
  • Using boards, mark out position of the external walls
  • Do the same for internal walls
  • Mark positions of foundations

All above should be shown on the ground using lime